| Milestones | Tue 2/2/99 | Thu 3/4/99 | |
| Start Elaboration Phase | Tue 2/2/99 | Tue 2/2/99 | |
| User-Interface Prototype Milestone | Wed 2/3/99 | Wed 2/3/99 | |
| Architectural Prototype Milestone (end Elaboration Phase) | Thu 3/4/99 | Thu 3/4/99 | |
| | | |
| Elaboration Phase | Tue 2/2/99 | Thu 3/4/99 | |
| Iteration E1 - Develop Architectural Prototype | Tue 2/2/99 | Thu 3/4/99 | |
| Business Modeling | Wed 2/3/99 | Fri 2/5/99 | |
| Find Business Workers and Entities | Wed 2/3/99 | Wed 2/3/99 | Business Designer |
| Describe Business Workers | Thu 2/4/99 | Thu 2/4/99 | |
| Describe Business Worker ‘BW1’ | Thu 2/4/99 | Thu 2/4/99 | Business Designer |
| Describe Business Worker ‘BW2’ | Thu 2/4/99 | Thu 2/4/99 | Business Designer |
| Describe Business Entities | Thu 2/4/99 | Thu 2/4/99 | |
| Describe Business Entity ‘BE1’ | Thu 2/4/99 | Thu 2/4/99 | Business Designer |
| Describe Business Entity ‘BE2’ | Thu 2/4/99 | Thu 2/4/99 | Business Designer |
| Review the Business Analysis Model | Fri 2/5/99 | Fri 2/5/99 | Business-Model Reviewer |
| Requirements | Wed 2/3/99 | Tue 2/9/99 | |
| Manage Dependencies | Wed 2/3/99 | Tue 2/9/99 | System Analyst |
| Detail Prioritized Use Cases | Wed 2/3/99 | Wed 2/3/99 | |
| Detail Use Case ‘UC1’ | Wed 2/3/99 | Wed 2/3/99 | Use-Case Author |
| Detail Use Case ‘UC2’ | Wed 2/3/99 | Wed 2/3/99 | Use-Case Author |
| Detail Use Case ‘UC3’ | Wed 2/3/99 | Wed 2/3/99 | Use-Case Author |
| Detail Use Case ‘UC4’ | Wed 2/3/99 | Wed 2/3/99 | Use-Case Author |
| Detail Use Case ‘UC5’ | Wed 2/3/99 | Wed 2/3/99 | Use-Case Author |
| Structure the Use Case Model | Thu 2/4/99 | Thu 2/4/99 | Architect |
| User-Interface Modeling | Wed 2/3/99 | Wed 2/3/99 | User-Interface Designer |
| User-Interface Prototyping | Wed 2/3/99 | Wed 2/3/99 | User-Interface Designer |
| Review Requirements | Fri 2/5/99 | Fri 2/5/99 | Requirements Reviewer |
| Analysis & Design (Architecture & Major Risks) | Fri 2/5/99 | Thu 2/18/99 | |
| Architectural Analysis | Fri 2/5/99 | Fri 2/5/99 | Architect |
| Prioritized Use-Case Analysis | Mon 2/8/99 | Mon 2/8/99 | |
| Analyze Use-Case ‘UC1’ | Mon 2/8/99 | Mon 2/8/99 | Designer |
| Analyze Use-Case ‘UC2’ | Mon 2/8/99 | Mon 2/8/99 | Designer |
| Analyze Use-Case ‘UC3’ | Mon 2/8/99 | Mon 2/8/99 | Designer |
| Analyze Use-Case ‘UC4’ | Mon 2/8/99 | Mon 2/8/99 | Designer |
| Architectural Design | Tue 2/9/99 | Tue 2/9/99 | |
| Describe Concurrency | Wed 2/10/99 | Wed 2/10/99 | Architect |
| Describe Distribution | Thu 2/11/99 | Thu 2/11/99 | Architect |
| Review the Architecture | Fri 2/12/99 | Fri 2/12/99 | Architecture Reviewer |
| Prioritized Subsystem Design | Mon 2/15/99 | Mon 2/15/99 | |
| Subsystem Design - Subsystem ‘S1’ | Mon 2/15/99 | Mon 2/15/99 | Designer |
| Subsystem Design - Subsystem ‘S2’ | Mon 2/15/99 | Mon 2/15/99 | Designer |
| Prioritized Class Design | Mon 2/15/99 | Mon 2/15/99 | |
| Class Design - Class ‘C1’ | Mon 2/15/99 | Mon 2/15/99 | Designer |
| Class Design - Class ‘C2’ | Mon 2/15/99 | Mon 2/15/99 | Designer |
| Class Design - Class ‘C3’ | Mon 2/15/99 | Mon 2/15/99 | Designer |
| Class Design - Class ‘C4’ | Mon 2/15/99 | Mon 2/15/99 | Designer |
| Prioritized Use-Case Design | Tue 2/16/99 | Tue 2/16/99 | |
| Design Use-Case ‘UC1’ | Tue 2/16/99 | Tue 2/16/99 | Designer |
| Design Use-Case ‘UC2’ | Tue 2/16/99 | Tue 2/16/99 | Designer |
| Database Design | Wed 2/17/99 | Wed 2/17/99 | Database Designer |
| Review the Design | Thu 2/18/99 | Thu 2/18/99 | Design Reviewer |
| Implementation (Architecture & Major Risks) | Mon 2/15/99 | Wed 2/24/99 | |
| Structure the Implementation Model | Mon 2/15/99 | Mon 2/15/99 | Architect |
| Plan System Integration | Fri 2/19/99 | Fri 2/19/99 | System Integrator |
| Plan Subsystem Integration | Mon 2/22/99 | Mon 2/22/99 | Implementer |
| Implement Prioritized Components | Mon 2/22/99 | Mon 2/22/99 | |
| Implement Component ‘c1’ | Mon 2/22/99 | Mon 2/22/99 | Implementer |
| Implement Component ‘c2’ | Mon 2/22/99 | Mon 2/22/99 | Implementer |
| Implement Component ‘c3’ | Mon 2/22/99 | Mon 2/22/99 | Implementer |
| Implement Component ‘c4’ | Mon 2/22/99 | Mon 2/22/99 | Implementer |
| Fix Defects | Tue 2/23/99 | Tue 2/23/99 | Implementer |
| Integrate Subsystems | Tue 2/23/99 | Tue 2/23/99 | Implementer |
| Integrate System | Wed 2/24/99 | Wed 2/24/99 | System Integrator |
| Test (Architecture & Major Risks) | Mon 2/22/99 | Tue 3/2/99 | |
| Plan Test (Integration & System) | Mon 2/22/99 | Mon 2/22/99 | Test Designer |
| Design Test (Integration & System) | Tue 2/23/99 | Tue 2/23/99 | Test Designer |
| Implement Test | Wed 2/24/99 | Wed 2/24/99 | Test Designer |
| Design Test Packages and Classes | Thu 2/25/99 | Thu 2/25/99 | Designer |
| Implement Test Components and Subsystems | Fri 2/26/99 | Fri 2/26/99 | Implementer |
| Execute Integration Test | Mon 3/1/99 | Mon 3/1/99 | Integration Tester |
| Execute System Test | Tue 3/2/99 | Tue 3/2/99 | System Tester |
| Execute Performance Tests | Mon 3/1/99 | Mon 3/1/99 | Performance Tester |
| Evaluate Test | Tue 3/2/99 | Tue 3/2/99 | Test Designer |
| Management | Tue 2/2/99 | Thu 3/4/99 | |
| Develop Iteration Plan | Tue 2/2/99 | Tue 2/2/99 | Project Manager |
| Staff the Project | Wed 2/3/99 | Wed 2/3/99 | Project Manager |
| Revisit Risk List | Tue 2/2/99 | Tue 3/2/99 | Project Manager |
| Evaluate the Iteration | Wed 3/3/99 | Wed 3/3/99 | Project Manager |
| Update Project Plan | Thu 3/4/99 | Thu 3/4/99 | Project Manager |
| | | |
| Environment | Tue 2/2/99 | Thu 3/4/99 | |
| Configure Processes | Tue 2/2/99 | Thu 2/11/99 | |
| Improve Processes | Fri 2/12/99 | Thu 3/4/99 | |
| Select and Acquire Tools | Tue 2/2/99 | Thu 3/4/99 | |
| Toolsmithing | Tue 2/2/99 | Thu 3/4/99 | |
| Support the Development | Tue 2/2/99 | Thu 3/4/99 | |
| Training | Mon 2/8/99 | Wed 2/17/99 | |