Iteration Plan

Task NameStartFinishResource Names
MilestonesTue 2/2/99Thu 3/4/99 
Start Elaboration PhaseTue 2/2/99Tue 2/2/99 
User-Interface Prototype MilestoneWed 2/3/99Wed 2/3/99 
Architectural Prototype Milestone (end Elaboration Phase)Thu 3/4/99Thu 3/4/99 
    
Elaboration PhaseTue 2/2/99Thu 3/4/99 
Iteration E1 - Develop Architectural PrototypeTue 2/2/99Thu 3/4/99 
Business ModelingWed 2/3/99Fri 2/5/99 
Find Business Workers and EntitiesWed 2/3/99Wed 2/3/99Business Designer
Describe Business WorkersThu 2/4/99Thu 2/4/99 
Describe Business Worker ‘BW1’Thu 2/4/99Thu 2/4/99Business Designer
Describe Business Worker ‘BW2’Thu 2/4/99Thu 2/4/99Business Designer
Describe Business EntitiesThu 2/4/99Thu 2/4/99 
Describe Business Entity ‘BE1’Thu 2/4/99Thu 2/4/99Business Designer
Describe Business Entity ‘BE2’Thu 2/4/99Thu 2/4/99Business Designer
Review the Business Analysis ModelFri 2/5/99Fri 2/5/99Business-Model Reviewer
RequirementsWed 2/3/99Tue 2/9/99 
Manage DependenciesWed 2/3/99Tue 2/9/99System Analyst
Detail Prioritized Use CasesWed 2/3/99Wed 2/3/99 
Detail Use Case ‘UC1’Wed 2/3/99Wed 2/3/99Use-Case Author
Detail Use Case ‘UC2’Wed 2/3/99Wed 2/3/99Use-Case Author
Detail Use Case ‘UC3’Wed 2/3/99Wed 2/3/99Use-Case Author
Detail Use Case ‘UC4’Wed 2/3/99Wed 2/3/99Use-Case Author
Detail Use Case ‘UC5’Wed 2/3/99Wed 2/3/99Use-Case Author
Structure the Use Case ModelThu 2/4/99Thu 2/4/99Architect
User-Interface ModelingWed 2/3/99Wed 2/3/99User-Interface Designer
User-Interface PrototypingWed 2/3/99Wed 2/3/99User-Interface Designer
Review RequirementsFri 2/5/99Fri 2/5/99Requirements Reviewer
Analysis & Design (Architecture & Major Risks)Fri 2/5/99Thu 2/18/99 
Architectural AnalysisFri 2/5/99Fri 2/5/99Architect
Prioritized Use-Case AnalysisMon 2/8/99Mon 2/8/99 
Analyze Use-Case ‘UC1’Mon 2/8/99Mon 2/8/99Designer
Analyze Use-Case ‘UC2’Mon 2/8/99Mon 2/8/99Designer
Analyze Use-Case ‘UC3’Mon 2/8/99Mon 2/8/99Designer
Analyze Use-Case ‘UC4’Mon 2/8/99Mon 2/8/99Designer
Architectural DesignTue 2/9/99Tue 2/9/99 
Describe ConcurrencyWed 2/10/99Wed 2/10/99Architect
Describe DistributionThu 2/11/99Thu 2/11/99Architect
Review the ArchitectureFri 2/12/99Fri 2/12/99Architecture Reviewer
Prioritized Subsystem DesignMon 2/15/99Mon 2/15/99 
Subsystem Design - Subsystem ‘S1’Mon 2/15/99Mon 2/15/99Designer
Subsystem Design - Subsystem ‘S2’Mon 2/15/99Mon 2/15/99Designer
Prioritized Class DesignMon 2/15/99Mon 2/15/99 
Class Design - Class ‘C1’Mon 2/15/99Mon 2/15/99Designer
Class Design - Class ‘C2’Mon 2/15/99Mon 2/15/99Designer
Class Design - Class ‘C3’Mon 2/15/99Mon 2/15/99Designer
Class Design - Class ‘C4’Mon 2/15/99Mon 2/15/99Designer
Prioritized Use-Case DesignTue 2/16/99Tue 2/16/99 
Design Use-Case ‘UC1’Tue 2/16/99Tue 2/16/99Designer
Design Use-Case ‘UC2’Tue 2/16/99Tue 2/16/99Designer
Database DesignWed 2/17/99Wed 2/17/99Database Designer
Review the DesignThu 2/18/99Thu 2/18/99Design Reviewer
Implementation (Architecture & Major Risks)Mon 2/15/99Wed 2/24/99 
Structure the Implementation ModelMon 2/15/99Mon 2/15/99Architect
Plan System IntegrationFri 2/19/99Fri 2/19/99System Integrator
Plan Subsystem IntegrationMon 2/22/99Mon 2/22/99Implementer
Implement Prioritized ComponentsMon 2/22/99Mon 2/22/99 
Implement Component ‘c1’Mon 2/22/99Mon 2/22/99Implementer
Implement Component ‘c2’Mon 2/22/99Mon 2/22/99Implementer
Implement Component ‘c3’Mon 2/22/99Mon 2/22/99Implementer
Implement Component ‘c4’Mon 2/22/99Mon 2/22/99Implementer
Fix DefectsTue 2/23/99Tue 2/23/99Implementer
Integrate SubsystemsTue 2/23/99Tue 2/23/99Implementer
Integrate SystemWed 2/24/99Wed 2/24/99System Integrator
Test (Architecture & Major Risks)Mon 2/22/99Tue 3/2/99 
Plan Test (Integration & System)Mon 2/22/99Mon 2/22/99Test Designer
Design Test (Integration & System)Tue 2/23/99Tue 2/23/99Test Designer
Implement TestWed 2/24/99Wed 2/24/99Test Designer
Design Test Packages and ClassesThu 2/25/99Thu 2/25/99Designer
Implement Test Components and SubsystemsFri 2/26/99Fri 2/26/99Implementer
Execute Integration TestMon 3/1/99Mon 3/1/99Integration Tester
Execute System TestTue 3/2/99Tue 3/2/99System Tester
Execute Performance TestsMon 3/1/99Mon 3/1/99Performance Tester
Evaluate TestTue 3/2/99Tue 3/2/99Test Designer
ManagementTue 2/2/99Thu 3/4/99 
Develop Iteration PlanTue 2/2/99Tue 2/2/99Project Manager
Staff the ProjectWed 2/3/99Wed 2/3/99Project Manager
Revisit Risk ListTue 2/2/99Tue 3/2/99Project Manager
Evaluate the IterationWed 3/3/99Wed 3/3/99Project Manager
Update Project PlanThu 3/4/99Thu 3/4/99Project Manager
    
EnvironmentTue 2/2/99Thu 3/4/99 
Configure ProcessesTue 2/2/99Thu 2/11/99 
Improve ProcessesFri 2/12/99Thu 3/4/99 
Select and Acquire ToolsTue 2/2/99Thu 3/4/99 
ToolsmithingTue 2/2/99Thu 3/4/99 
Support the DevelopmentTue 2/2/99Thu 3/4/99 
TrainingMon 2/8/99Wed 2/17/99