Example: Risk List

**Course Registration System

Risk List**

Version 2.0

Revision History

DateVersionDescriptionAuthor
18/Jan/991.0Risks identified at the beginning of the Inception Phase.Rick Bell
12/Feb/992.0Updated risk list at beginning of Elaboration Phase. No new risks. Eliminate risk of funding problems. Downgrade criticality of other risks.Rick Bell

Risk List

Project risk is evaluated at least once per iteration and documented in this table. The risks of the greatest magnitude are listed first in the table. (This list was last updated at the beginning of the Elaboration Phase.)

Risk Ranking/ MagnitudeRisk Description & ImpactMitigation Strategy and/or Contingency Plan
8Volume of students logged on during peak hours of the registration period may significantly degrade system performance.Further develop prototype to obtain more accurate numbers.
7R1 and R2 Releases may slip and not be available by September 1999 - the start of the Registration Period.Monitor progress against the schedule & milestones. Update effort to complete and time to complete on a regular basis.
5Interfaces to the old legacy Billing and Course Catalog Systems may introduce performance and response time issues.Continue to develop prototype. Monitor this issue at weekly progress meetings.
4One Developer position remains unfilled. If not filled by the start of the Construction Phase, the schedule could slip by up to 5 weeks.Contact local recruiting agencies. Action: Rick Bell.
3Strike Action of College Facility Union Workers may impact project schedule if IT services are unavailable.Monitor.