Example: Iteration Plan
Course Registration System
Iteration Plan Preliminary Iteration (Inception)
Version 1.1
Revision History
| Date | Version | Description | Author |
|---|---|---|---|
| 18/Jan/1999 | 1.0 | Initial Release | Rick Bell |
| 22/Jan/1999 | 1.1 | Revised the high level schedule. Adjusted the budget. | Rick Bell |
| | ||
Table of Contents
- Objectives
- Scope
- References
-
- Plan
-
4.1 [Iteration Activities](#Iteration Activities)
-
4.2 [Iteration Schedule](#Iteration Schedule)
-
4.3 [Iteration Deliverables](#Iteration Deliverables)
- [Use Cases](#Use Cases)
- [Evaluation Criteria](#Evaluation Criteria)
Iteration Plan
- Objectives
This Iteration Plan describes the detailed plans for the Preliminary Iteration of the C-Registration System Project. During this iteration, the requirements of the system will be defined and the high level plan for execution of the full project will be developed. This first iteration will conduct a thorough analysis on the business case for the system and will result in a decision on whether the project will proceed.
2. Scope
The Preliminary Iteration Plan applies to the C-Registration System project being developed by Wylie College Information Systems for Wylie College. This document will be used by the Project Manager and by the project team.
3. References
Applicable references are:
- Course Registration System Vision Document, WyIT387, V1.0, Wylie College IT.
- Course Registration System Stakeholder Requests Document, WyIT389, V1.0, 1998, Wylie College IT.
- Course Registration System Glossary, WyIT406, V1.0, 1998, Wylie College IT.
- Course Registration System Inception Phase Schedule, V1.0, 1999, Wylie College IT.
- Course Registration System Project Plan, WyIT418, V1.0, 1999, Wylie College IT.
4. Plan
The Preliminary Iteration will develop the product requirements and establish the business case for the C-Registration System. The major use cases will be developed as well as the high level Project Plan. At the end of this iteration, Wylie College will decide whether to fund and proceed with the project based upon the business case.
4.1 Iteration Activities
The following table illustrates the high level activities with their planned start and end dates.
| Activity | Start Date | End Date |
|---|---|---|
| Business Modeling | Dec 1, 1998 | Dec 22, 1998 |
| Requirements Definition | Dec 1, 1998 | Jan 19, 1999 |
| Configuration Management Setup | Dec 1, 1998 | Jan 14, 1999 |
| Management | Dec 1, 1998 | Jan 19, 1999 |
4.2 Iteration Schedule
The detailed schedule showing all tasks and the assigned responsibilities is contained in the following schedule:
| Task Name | Duration | Start | Finish | Resource Names | — | — | — | — | — | Milestones | 45 days | Tue 12/1/98 | Mon 2/1/99 | | Start | 0 days | Tue 12/1/98 | Tue 12/1/98 | | Business Case Review Milestone (end Inception Phase) | 0 days | Mon 2/1/99 | Mon 2/1/99 | | Inception Phase | 45 days | Tue 12/1/98 | Mon 2/1/99 | | Preliminary Iteration | 45 days | Tue 12/1/98 | Mon 2/1/99 | | Business Modeling | 18 days | Tue 12/1/98 | Thu 12/24/98 | | Capture a Common Vocabulary | 9 days | Tue 12/1/98 | Fri 12/11/98 | Business-Process Analyst | Find Business Actors and Use Cases | 3 days | Wed 12/9/98 | Fri 12/11/98 | Business-Process Analyst | Describe Business Use Cases | 9 days | Tue 12/1/98 | Fri 12/11/98 | | Describe Business Use Case ‘BUC1’ | 9 days | Tue 12/1/98 | Fri 12/11/98 | Business Designer | Describe Business Use Case ‘BUC2’ | 9 days | Tue 12/1/98 | Fri 12/11/98 | Business Designer | Structure the Business Use-Case Model | 14 days | Tue 12/1/98 | Fri 12/18/98 | Business-Process Analyst | Review Business Use-Case Model | 4 days | Mon 12/21/98 | Thu 12/24/98 | Business-Model Reviewer | Requirements | 40 days | Tue 12/1/98 | Mon 1/25/99 | | Develop Vision | 25 days | Tue 12/1/98 | Mon 1/4/99 | System Analyst | Elicit Stakeholder Requests | 4 days | Tue 1/5/99 | Fri 1/8/99 | System Analyst | Manage Dependencies | 26 days | Tue 12/1/98 | Tue 1/5/99 | System Analyst | Capture a Common Vocabulary | 10 days | Wed 12/23/98 | Tue 1/5/99 | System Analyst | Find Actors and Use Cases | 10 days | Wed 12/23/98 | Tue 1/5/99 | System Analyst | Prioritize Use Cases | 10 days | Tue 1/12/99 | Mon 1/25/99 | Architect | Define System & Constraints | 1 day | Mon 1/11/99 | Mon 1/11/99 | System Analyst | Configuration Management | 34 days | Tue 12/1/98 | Fri 1/15/99 | | Establish CM Practices | 14 days | Tue 12/1/98 | Fri 12/18/98 |
4.3 Iteration Deliverables
The following deliverables or artifacts will be generated and reviewed during the Preliminary Iteration:
| Artifact Set | Deliverable | Responsible Owner |
|---|---|---|
| Business Modeling Set | Glossary Business Use Case Model Supplementary Business Spec. Business Use Case Realization | Bob Collings Yee Chung Bob Collings Yee Chung |
| Requirements Set | Vision Document Stakeholder Requests Document Use Case Specifications Supplementary Specification Requirements Attributes Document Use Case Model (and Model Survey) | Sue Gamble Bob King Sue Gamble Sue Gamble Sue Gamble Sue Gamble |
| Management Set | Preliminary Iteration Plan Project Plan Project Schedule Project Risk List Measurement Plan Business Case Document Status Assessment Preliminary Iteration Assessment Configuration Management Plan | Rick Bell Rick Bell Rick Bell Rick Bell Rick Bell Rick Bell Rick Bell & Carol Ming Rick Bell & Carol Ming Simon Jones |
| Standards and Guidelines | Requirements Attributes Guidelines Configuration Management Environment | Simon Jones Simon Jones |
5. Resources**> 5.1 Staffing Resources**
The staffing requirements for the Preliminary Iteration are:
Project Management
Project Management Rick Bell
Business Modeling Group
Business Modeling Manager Bob King
Business-Process Analysts Bill Collings, Glen Fox
Business Designer Yee Chung
Business-Model Reviewer Abu Zony
Systems Engineering
Systems Engineering Manager Carol Ming
Systems Analysts Sue Gamble, <TBD>
Architect Steve Johnson
Software Engineering
Process Engineer (CM) Simon Jones
The project organization chart and the staffing requirements for the full project will be contained within the Project Plan [5].
5.2 Financial Resources
The following table shows the budget for the Preliminary Iteration. Wylie College has secured $150,000 in funds for this first iteration.

5.3 Equipment & Facilities Resources
The Inception Phase requires the following computer equipment, which has already been acquired by the Information Systems department:
- 4 PCs (Windows 95 , MS Office, Rational Rose, RequisitePro)
- 6 Monitors
- 1 Printer
- Access to the Wylie College Server.
The Wylie College Information Systems department has sufficient office space and furniture to meet the needs of this iteration.
6. Use Cases
During the Preliminary Iteration, all significant use cases and actors will be identified. The basic flows and key alternative flows of each use case will be determined and documented in the Use Case Specifications. The design and implementation of use cases will begin in the next iteration.
7. Evaluation Criteria
The primary goal of the Preliminary Iteration is to define the system to the level of detail required to make a sound business judgment on the viability of the project from a business prospective. At the completion of the iteration, a review of the Business Case will arrive at a Go / No Go decision for the project.
Each deliverable developed during the iteration will be peer reviewed and subject to approval from the team.