Course Registration System

T1 & T2 Iteration Plan

Version 1.0

Revision History

DateVersionDescriptionAuthor
May 15/19991.0Initial Plan for 2 iterations of the Transition Phase: T1 and T2.Rick Bell

Table of Contents

1. Introduction

1.1 Purpose

1.2 Scope

1.3     Definitions, Acronyms and Abbreviations

1.4 References

1.5 Overview

2. Plan

3. Resources

4.       Use Cases

5.       Evaluation Criteria

Iteration Plan

1.Introduction

1.1Purpose

This Iteration Plan describes the detailed plans for the first two iterations of the Transition Phase.

The first iteration (T1) of the Transition Phase packages and installs the R1.0 version of the C-Registration System. This release contains all key functionality for course registration with the exception of submission and viewing of student marks.

The second iteration (T2) of the Transition Phase packages and installs the R2.0 version. This release contains all key functionality as defined in the Vision Document [1].

1.2Scope

This Iteration Plan applies to the C-Registration System project being developed by Wylie College Information Systems for Wylie College. This document will be used by the Project Manager, Deployment Manager, and by the project team.

1.3Definitions, Acronyms and Abbreviations

See the Glossary [3].

1.4References

Applicable references are:

  1. Course Registration System Vision Document, WyIT387, V1.0, Wylie College IT.
  2. Course Registration System Stakeholder Requests Document, WyIT389, V1.0, 1998, Wylie College IT.
  3. Course Registration System Glossary, WyIT406, V1.0, 1998, Wylie College IT.
  4. Course Registration System Software Development Plan, WyIT418, V2.0, 1999, Wylie College IT.
  5. Course Registration System Schedule for the Transition Phase, V1.0, Wylie College IT.

1.5Overview

This document provides the detailed schedule for this iteration including all milestones.  It also describes the required resources (staffing, financial, and equipment), expected status of use cases, and evaluation criteria for completion of the iteration.

2.Plan

The first iteration (T1) will commence when the R1.0 software baseline is available from the development team. The software will be packaged and the distribution media created. The Transition team will create the User Manual and will install the software on the Wylie College Server and selected client PCs on campus. The Transition Team is responsible for conducting the User Acceptance Tests and obtaining signoff from the Wylie College representative.

In addition, the client software will be setup on an FTP site so that any client P.C. with a valid ID and Internet access may download the client portion to their P.C.

The transition team provides training and support to the Wylie College Registrar and administration staff following installation of the software.

The second iteration (T2) will commence when the R2.0 software baseline is available from the development team. The activities for preparing the R2.0 Release are the same as defined above for R1.0, with the exception that R2.0 must convert and import the R1.0 data.

The primary use cases that form Release 1.0 are:

  • Logon
  • Close Registration
  • Register for Courses
  • Interface to Course Catalog Database
  • Interface to Finance System
  • Maintain Student Information
  • Maintain Professor Information

The primary use cases that form Release 2.0 are:

  • Submit Student Grades
  • View Grades
  • Select Courses to Teach
  1. Iteration Activities

The following table illustrates the high level activities for T1 and T2 iterations with their planned start and end dates.

T1 Iteration - Release 1.0

ActivityStart DateEnd Date
Produce SoftwareMay 27, 1999June 1, 1999
Package & Distribute ReleaseJune 2, 1999June 7, 1999
Acceptance TestJune 10, 1999June 11, 1999

T1 Iteration - Release 2.0

ActivityStart DateEnd Date
Produce SoftwareJune 30, 1999July 2, 1999
Package & Distribute ReleaseJuly 5, 1999July 8, 1999
Migrate R1.0 DataJune 30, 1999July 20, 1999
Acceptance TestJuly 13, 1999July 14, 1999
  1. Iteration Schedule

The detailed schedule showing all tasks and the assigned responsibilities is contained in the following Microsoft Project schedule [5]:

Task NameStartFinish
MilestonesThu 5/27/99Wed 7/14/99
Start T1 IterationThu 5/27/99Thu 5/27/99
Release R1.0 AcceptanceFri 6/11/99Fri 6/11/99
Start T2 IterationWed 6/30/99Wed 6/30/99
Release 2.0 AcceptanceWed 7/14/99Wed 7/14/99
   
Transition PhaseThu 5/27/99Tue 7/20/99
Iteration T1 - Release 1Thu 5/27/99Wed 6/16/99
DeploymentThu 5/27/99Wed 6/16/99
Produce SoftwareThu 5/27/99Tue 6/1/99
Installation scriptsThu 5/27/99Fri 5/28/99
User documentationThu 5/27/99Tue 6/1/99
Configuration dataThu 5/27/99Fri 5/28/99
Package SoftwareWed 6/2/99Thu 6/3/99
Distribute SoftwareFri 6/4/99Mon 6/7/99
Install SoftwareTue 6/8/99Wed 6/9/99
Provide Help and Assistance to the UsersThu 6/10/99Wed 6/16/99
Acceptance TestingThu 6/10/99Fri 6/11/99
Iteration T2 - Release 2Wed 6/30/99Tue 7/20/99
DeploymentWed 6/30/99Tue 7/20/99
Produce SoftwareWed 6/30/99Fri 7/2/99
Installation scriptsWed 6/30/99Wed 6/30/99
User documentationWed 6/30/99Fri 7/2/99
Configuration dataWed 6/30/99Wed 6/30/99
Additional programs for migration: data conversionWed 6/30/99Thu 7/1/99
Package SoftwareMon 7/5/99Tue 7/6/99
Distribute SoftwareWed 7/7/99Thu 7/8/99
Install SoftwareFri 7/9/99Mon 7/12/99
MigrationThu 7/15/99Tue 7/20/99
Provide Help and Assistance to the UsersTue 7/13/99Mon 7/19/99
Acceptance TestingTue 7/13/99Wed 7/14/99
  1. Iteration Deliverables

The following deliverables will be generated and reviewed during the T1 & T2 Iterations:

IterationDeliverableResponsible Owner
T1Installation Scripts User Manual Configuration Data Software Installation Media Release Notes User Training Materials Acceptance Test SignoffP. Armstrong G. Mandu P. Armstrong P. Armstrong G. Mandu G. Mandu K. Stone / R. Bell
T2Installation Scripts User Manual Configuration Data Data Migration Utility Program Software Installation Media Release Notes User Training Materials Acceptance Test SignoffP. Armstrong G. Mandu P. Armstrong B. MacDonald P. Armstrong G. Mandu G. Mandu K. Stone / R. Bell

3.Resources

  1. Staffing Resources

During the T1 & T2 Iterations the staffing requirements are:

Project Management

Project Management Rick Bell

Deployment Management Greg Mandu

Software Engineering

Developer Beth MacDonald

Test

Test Manager Kerry Stone

Deployment

Field Engineer Phil Armstrong

The project organization chart and the staffing requirements for the full project are contained within the Project Plan [4].

  1. Financial Resources

The following table shows the budget for the T1 & T2 Iterations.

Described in Content Above

  1. Equipment & Facilities Resources

The T1 & T2 Iterations require no additional equipment or facilities beyond those items already identified and obtained for the Construction Phase.

The existing Wylie College web site will be used for user support and downloading the client software.

The printing of the User Manuals will be contracted to the Wylie College Print Shop.

**4.**Use Cases

The T1 & T2 Iterations do not include the development of any use cases.

The primary use cases that form Release 1.0 are:

  • Logon
  • Close Registration
  • Register for Courses
  • Interface to Course Catalog Database
  • Interface to Finance System
  • Maintain Student Information
  • Maintain Professor Information

The primary use cases that form Release 2.0 are:

  • Submit Student Grades
  • View Grades
  • Select Courses to Teach

**5.**Evaluation Criteria

The primary goal of the T1 and T2 Iterations is to install R1.0 and R2.0 and obtain user acceptance of the software.

In addition, the following criteria must be met prior to completion of the T1 and T2 Iterations:

The R1.0 and R2.0 releases must not contain any critical or high priority defects.

R2.0 must be installed and operational 3 weeks prior to the start of student registration for the Fall Semester.

R1.0 and R2.0 must pass user acceptance and must be formally signed off by the Wylie College representative.

User training must be completed.

Web site must be established for product support.

User Manuals must be printed and available either through the IT department or the Wylie College Book Store.

The process and resources to provide ongoing user support must be established.