**Collegiate Sports Paging Service

Iteration Plan**

 Version 1.0

 Revision History

DateVersionDescriptionAuthor
October 6, 19991.0Initial versionContext Integration
Table of Contents

Introduction

Purpose

This Iteration Plan describes the detailed plans for the Preliminary Iteration of the Project. During this iteration, the requirements of the system will be defined and the high level plan for execution of the full project will be developed. This first iteration will conduct a thorough analysis on the business case for the system and will result in a decision on whether the project will proceed.

Scope

The Preliminary Iteration Plan applies to the project being developed by Context Integration for WebNewsOnLine. This document will be used by the Project Manager and by the project team.

Definitions, Acronyms and Abbreviations

See Glossary document.

References

  1. CSPS Vision 1.0
  2. CSPS Requirements Management Plan 1.0

Plan

The Preliminary Iteration will develop the product requirements and establish the business case for the Collegiate Sports Paging System. The major use cases will be developed as well as the high level Project Plan. At the end of this iteration, will decide whether to fund and proceed with the project based upon the business case.

Iteration Tasks

The following table illustrates the tasks with their planned start and end dates.

TaskStartEnd
INCEPTIONFri 10/1/99Mon 10/25/99
Begin InceptionFri 10/1/99Fri 10/1/99
Inception Kick-offMon 10/4/99Wed 10/6/99
Add tasks to project plan for specific project technology using ContextWISE cartridgesMon 10/4/99Mon 10/4/99
Assemble Change Control BoardMon 10/4/99Tue 10/5/99
Create and baseline Change Control PlanTue 10/5/99Tue 10/5/99
Obtain Sign-offTue 10/5/99Tue 10/5/99
Inception Kick-off MeetingTue 10/5/99Wed 10/6/99
Prepare for inception kick-off meetingTue 10/5/99Wed 10/6/99
Hold Inception Kick-off MeetingWed 10/6/99Wed 10/6/99
Inception Kick-off CompletedWed 10/6/99Wed 10/6/99
Inception DeliverablesWed 10/6/99Thu 10/14/99
Hold Requirements WorkshopWed 10/6/99Thu 10/7/99
Project Vision created, reviewed, and signed offWed 10/6/99Thu 10/7/99
Preliminary Use Case Model (10-20% complete) created and placed under revision controlThu 10/7/99Mon 10/11/99
Preliminary Use Case Survey created, reviewed, and signed offMon 10/11/99Tue 10/12/99
Preliminary Supplementary Specifications created, reviewed, and signed offTue 10/12/99Tue 10/12/99
Business Case created, reviewed, and signed offTue 10/12/99Tue 10/12/99
Preliminary Project Glossary created, reviewed, and signed offTue 10/12/99Tue 10/12/99
Preliminary Creative Design Brief created, reviewed, and signed offWed 10/6/99Thu 10/7/99
Preliminary Site Map & Use-Case Navigation Mapping created, reviewed, and signed offThu 10/7/99Fri 10/8/99
Creative Design Comps created, reviewed, and signed offFri 10/8/99Mon 10/11/99
Preliminary Content Plan created, reviewed, and signed off (if applicable)Wed 10/6/99Wed 10/6/99
User Interface Prototype (optional) created, reviewed, and signed offWed 10/6/99Wed 10/6/99
Reports Prototype (optional) created, reviewed, and signed offTue 10/12/99Thu 10/14/99
Develop Preliminary Technology AlternativesWed 10/6/99Thu 10/7/99
Establish contact with appropriate Context GurusTue 10/12/99Wed 10/13/99
Preliminary Knowledge Transfer Plan & Schedule created, reviewed, and signed offWed 10/13/99Wed 10/13/99
Validate/Invalidate Assumption from Inception proposalWed 10/13/99Thu 10/14/99
Obtain Sign-offThu 10/14/99Thu 10/14/99
Inception Deliverables CompleteThu 10/14/99Thu 10/14/99
Inception Wrap-upThu 10/14/99Mon 10/25/99
Conduct Quality Check Meeting with ClientThu 10/14/99Thu 10/14/99
Conduct Quality AssuranceThu 10/14/99Fri 10/15/99
Hold Context Lessons Learned MeetingThu 10/14/99Thu 10/14/99
First project estimates created, reviewed, and signed off (+75%, -60%)Thu 10/14/99Mon 10/18/99
Full Project Iterative Delivery Plan created, reviewed, and signed offMon 10/18/99Tue 10/19/99
Create proposal for Elaboration PhaseThu 10/14/99Fri 10/15/99
Create Software Project LogFri 10/15/99Fri 10/15/99
Prepare for Inception CheckpointFri 10/15/99Mon 10/18/99
Have team, including client project manager, complete the work release sign-off formMon 10/18/99Tue 10/19/99
Deliver proposal for Elaboration PhaseTue 10/19/99Thu 10/21/99
Inception Checkpoint Review and Go/No Go DecisionThu 10/21/99Fri 10/22/99
Move appropriate deliverables from Project Homepage to IAN ArtifactsFri 10/22/99Mon 10/25/99
Inception CompleteMon 10/25/99Mon 10/25/99

The following deliverables or artifacts will be generated and reviewed during the Preliminary Iteration:

Artifact SetDeliverableResponsible Owner
Business Modeling SetGlossaryBrian Egler Brian Egler Brian Egler Brian Egler
Requirements SetVision Document Use Case Specifications Supplementary Specification Use Case Model (and Model Survey)Brian Egler Brian Egler Ed Post Ken Perch Ken Perch
Management SetPreliminary Iteration Plan Project Plan Project Schedule Project Risk List Status Assessment Preliminary Iteration Assessment Configuration Management PlanMary Durham Mary Durham Mary Durham Mary Durham Mary Durham Mary Durham Mary Durham Mary Durham Ken Perch
Standards and GuidelinesConfiguration Management EnvironmentKen Perch

Resources

The project staffing for this iteration can be viewed as follows:

Financial Resources

The budget for this iteration is $150,000. WebNewsOnLine has secured this funding.

Use Cases

During the Preliminary Iteration, all significant use cases and actors will be identified. The basic flows and key alternative flows of each use case will be determined and documented in the Use Case Specifications. The design and implementation of use cases will begin in the next iteration.

Evaluation Criteria

The primary goal of the Preliminary Iteration is to define the system to the level of detail required to make a sound business judgment on the viability of the project from a business prospective. At the completion of the iteration, a review of the Business Case will arrive at a Go / No Go decision for the project.

Each deliverable developed during the iteration will be peer reviewed and subject to approval from the team.

Criteria for evaluation can be found in the Test Plan.