**Collegiate Sports Paging System

Status Assessment

Version 1.0**

 Revision History

DateVersionDescriptionAuthor
November 22, 19991.0Weekly assessmentContext Integration

Table of Contents

  • Introduction
  • Resources
  • [Top 10 Risks](#Top 10 Risks)
  • [Technical Progress](#Technical Progress)
  • [Major Milestone Results](#Major Milestone Results)
  • [Total Project/Product Scope](#Total Project/Product Scope)
  • [Action Items and Follow-Through](#Action Items and Follow-Through)

Introduction

Purpose

This status assessment reviews the current status of the project with respect to resources, budget, schedule, risk, technical issues, and management issues. Any actions arising from this assessment will be summarized in this document.

Scope

This assessment reviews all aspects of the Collegiate Sports Paging System.

Definitions, Acronyms and Abbreviations

See Glossary.

References

  1. CSPS Vision 1.0
  2. CSPS Requirements Management Plan 1.0
  3. CSPS Iteration Plan 1.0
  4. CSPS Creative Design Brief 1.0
  5. CSPS Supplementary Specification 1.0
  6. CSPS Iteration Plan 3.0
  7. CSPS Risk List 3.0

Resources

Personnel/Staffing

Elaboration staff will be leaving the project as they are no longer needed. Departing staff include Brian Egler, Business Analyst, and Mark Grimes, Creative Designer. Staff whose contribution will increase are Justin Woddis, Implementer, various implementation subcontractors reporting to Justin, and Chris Curvey, Tester.

Financial Data

The project is delivered on a fixed-price basis. As such, no financial data need be reported.

Top 10 Risks

The project risks and their mitigation strategies can be found in the Risk List.

Technical Progress

During this iteration, the following artifacts were produced:

  • User-Interface Prototype
  • Analysis Model
  • Design Model
  • Software Architecture Document
  • Integration Build Plan
  • Architectural Prototype - Software Baseline
  • Test Drivers, Stubs, Data, & Scripts
  • Test Procedures
  • Test Evaluation Report
  • Iteration Plan
  • Status Assessment
  • Iteration Assessment
  • Test Plan
  • Design Guidelines
  • User-Interface Guidelines

The following artifacts were updated:

  • Glossary
  • Vision Document
  • Use Case Specifications
  • Supplementary Specification
  • Use Case Model and Model Survey
  • Project Plan
  • Project Schedule
  • Project Risk List

Major Milestone Results

The following table lists iteration milestones and their status at the end of this iteration.

MilestonePlannedActualComments
Use case design complete11/3/199911/4/1999One-day slip for documentation
Software Architecture document complete11/22/199911/21/1999No major issues raised with use cases during architectural design
Test Plans Complete11/9/199911/10/1999Mapped to use cases

Total Project/Product Scope

No scope changes occurred during this period.

Action Items and Follow-Through

The following action items were carried forward from last week or initiated this week:

ItemAssignedDueStatus
Validate color scheme for UI with advertiser rep.Mark Grimes11/19/1999Closed - minor change made to UI design guidelines
Investigate multi-tiered gateway approachKen Perch11/25/1999Open