**Collegiate Sports Paging System
Status Assessment
Version 1.0**
Revision History
| Date | Version | Description | Author |
| November 22, 1999 | 1.0 | Weekly assessment | Context Integration |
Table of Contents
- Introduction
- Resources
- [Top 10 Risks](#Top 10 Risks)
- [Technical Progress](#Technical Progress)
- [Major Milestone Results](#Major Milestone Results)
- [Total Project/Product Scope](#Total Project/Product Scope)
- [Action Items and Follow-Through](#Action Items and Follow-Through)
Introduction
Purpose
This status assessment reviews the current status of the project with respect to resources, budget, schedule, risk, technical issues, and management issues. Any actions arising from this assessment will be summarized in this document.
Scope
This assessment reviews all aspects of the Collegiate Sports Paging System.
Definitions, Acronyms and Abbreviations
See Glossary.
References
- CSPS Vision 1.0
- CSPS Requirements Management Plan 1.0
- CSPS Iteration Plan 1.0
- CSPS Creative Design Brief 1.0
- CSPS Supplementary Specification 1.0
- CSPS Iteration Plan 3.0
- CSPS Risk List 3.0
Resources
Personnel/Staffing
Elaboration staff will be leaving the project as they are no longer needed. Departing staff include Brian Egler, Business Analyst, and Mark Grimes, Creative Designer. Staff whose contribution will increase are Justin Woddis, Implementer, various implementation subcontractors reporting to Justin, and Chris Curvey, Tester.
Financial Data
The project is delivered on a fixed-price basis. As such, no financial data need be reported.
Top 10 Risks
The project risks and their mitigation strategies can be found in the Risk List.
Technical Progress
During this iteration, the following artifacts were produced:
- User-Interface Prototype
- Analysis Model
- Design Model
- Software Architecture Document
- Integration Build Plan
- Architectural Prototype - Software Baseline
- Test Drivers, Stubs, Data, & Scripts
- Test Procedures
- Test Evaluation Report
- Iteration Plan
- Status Assessment
- Iteration Assessment
- Test Plan
- Design Guidelines
- User-Interface Guidelines
The following artifacts were updated:
- Glossary
- Vision Document
- Use Case Specifications
- Supplementary Specification
- Use Case Model and Model Survey
- Project Plan
- Project Schedule
- Project Risk List
Major Milestone Results
The following table lists iteration milestones and their status at the end of this iteration.
| Milestone | Planned | Actual | Comments |
| Use case design complete | 11/3/1999 | 11/4/1999 | One-day slip for documentation |
| Software Architecture document complete | 11/22/1999 | 11/21/1999 | No major issues raised with use cases during architectural design |
| Test Plans Complete | 11/9/1999 | 11/10/1999 | Mapped to use cases |
Total Project/Product Scope
No scope changes occurred during this period.
Action Items and Follow-Through
The following action items were carried forward from last week or initiated this week:
| Item | Assigned | Due | Status |
| Validate color scheme for UI with advertiser rep. | Mark Grimes | 11/19/1999 | Closed - minor change made to UI design guidelines |
| Investigate multi-tiered gateway approach | Ken Perch | 11/25/1999 | Open |